In the ‘Manage tasks’ page, tasks will appear as ‘Scheduled’ only after the first task (the task set to trigger the earliest) from the task list has been triggered.
Example
If you have three tasks in a task list:
- 10 days before Start date
- On the start date
- 10 days after the start date
You’ll only see the second and third tasks in Manage tasks as 'scheduled' after the first task is triggered. Until then, Bob doesn’t mark them as “scheduled,” which is why they don’t yet display in the system.
If a task list contains only one task, that single task will not show up as scheduled until its trigger date.