I can't see tasks appearing as “scheduled” under Manage tasks

  • Jun 15, 2025 8:16 PM UTC
  • 1 reply
  • 170 views
  • Translate All

Anna Uriadnykova
Bobber

In the ‘Manage tasks’ page, tasks will appear as ‘Scheduled’ only after the first task (the task set to trigger the earliest) from the task list has been triggered.

Example
If you have three tasks in a task list:

  1. 10 days before Start date
  2. On the start date
  3. 10 days after the start date

You’ll only see the second and third tasks in Manage tasks as 'scheduled' after the first task is triggered. Until then, Bob doesn’t mark them as “scheduled,” which is why they don’t yet display in the system.

If a task list contains only one task, that single task will not show up as scheduled until its trigger date.

1 reply

LisaDalsgaard

Thank you for this post! I hope you can help me clarify something.

I have a task list that is triggered based on the termination date. The tasks are scheduled as follows:

  • 3 months after termination date

  • 2 years after termination date

  • 6 years after termination date

  • 7 years after termination date

  • 10 years after termination date

I have two questions regarding this:

  1. In the “manage task” overview I can see scheduled tasks for "2 years after termination date" for all employees who were terminated before this task list was created and who has already passed the “3 months” review. This makes sense as it becomes the first task related to their profiles. However, I don’t understand why the rest of the tasks in the list are not scheduled for them?

  2. We had a termination last month. I would have expected the "3 months after termination date" task to be scheduled, since the termination date is the trigger. Will this task only appear on the date - 90 days after the termination date? If so, will the rest of the tasks then be scheduled according to their respective timelines and visible in the overview or how is it?

Translate